Exilles hydropower plant
The project
The project involves the construction of a run-ofriver hydroelectric plant, with its main components being the intake structure, the diversion channel, the loading basin, the penstock, the powerstation, and the discharge channel. To stabilize the slope and safely excavate for the power station, variable-height anchored micropile walls have been implemented. Frosio Next has provided services including the review of the executive project, the drafting of technical specifications and bidding documents,project management, safety coordination during the design and execution phases (CSP/CSE), as well as assistance during the plant commissioning.
Services provided by Frosio Next:
- Executive project review
- ELMEC works – contract specifications
- Works supervision
- Safety coordination during design phase
- Safety coordination during execution phase
- Equipment tests assistance
- Plant Start-up assistance

2021
Exilles (Turin province), Italy
EXECUTIVE PROJECT REVIEW
ELMEC WORKS – CONTRACT SPECIFICATIONS
WORKS SUPERVISION
SAFETY COORDINATION DURING DESIGN PHASE
SAFETY COORDINATION DURING EXECUTION PHASE
EQUIPMENT TESTS ASSISTANCE
PLANT START-UP ASSISTANCE
New Exilles hydropower plant
1319 kW
515,78 m
0,55 m3/s